Rock to Road

Features Roads & Bridges Roads & Paving
Six-point plan proposed to shorten wait time of Ontario utility locates

September 18, 2020  By Jay Koblun



Contractors in Ontario are seeing wait times of sometimes more than 30 days for utility locates to be completed. The Residential and Civil Construction Alliance of Ontario (RCCAO) and its stakeholders are asking the province to speed-up response times.

“This is a really important issue for our members in the residential and civil sectors,” said Andy Manahan, executive director at the RCCAO. “These contractors work on road systems, water sewer systems, and other similar sectors. Work cannot begin on a project until utility locates have been completed and, according to Ontario legislation, a utility locate should be completed within five days. We’re waiting weeks or even months for those markings.”

Utility location is the process of identifying and labelling public utility mains that are underground. These mains may include lines for telecommunication, electricity distribution, natural gas, cable television, fibre optics, traffic lights, street lights, storm drains, water mains, and wastewater pipes.

Andy Manahan, executive director of the Residential and Civil Construction Alliance of Ontario. Photo: RCCAO

“You’ve probably seen utility markings in your own neighbourhood—Enbridge, Bell, and Rogers, are all companies in Ontario that use them—and they would likely subcontract those requests out to a company. Utility locates are required for contractors and homeowners. For example, if someone wants to do digging in their garden around their house and is going to dig a couple feet deep, they need to get the necessary markings done, which is typically paint on a lawn telling a contractor or homeowner where the utility is and at what depth,” said Manahan.

Advertisement

The RCCAO recently sent a proposal to the offices of Premier Doug Ford and to the Minister of Government and Consumer Services, as well as 19 MPPs who are on the Standing Committee on Finance and Economic Affairs, outlining six measures it says will improve the Ontario One Call system.

Ontario One Call is a not-for-profit organization that facilitates excavation locate requests to ensure homeowners, excavators and infrastructure owners are safe when digging. Ontario One Call notifies infrastructure owners of excavation requests.

Manahan said late locate deliveries impact the roadbuilding industry.

“Late locates really impact road crews. If you have municipalities that want to co-ordinate effectively, sometimes road and sewer work are done at the same time. Not only for municipal roads, but private sectors too, it’s across the board,” Manahan.

Patrick McManus, executive director of the Ontario Sewer and Watermain Construction Association (OSWCA), said the association has roughly 800 contractors and supplier members who build, service, design, manufacture and supply the municipal; infrastructure sector that deals with sewer, water main, and storm water infrastructure. And the biggest problem with late locate deliveries is contractors not able to start digging.

“Contractors can’t start digging until we have locates on the ground,” he said. “The five-day limit has not been respected. Over time the delivery of locates has become worse, seeing them delivered later and later every year. The reason it is such a problem is, in our business, we don’t work 12 months of the year. As soon as the ground freezes, we stop working. We’re limited to an eight- or nine-month long construction season. If contractors have a project start date of July 1, with an expected close date of November 15, three weeks matters a lot. If a project is getting pushed back that much, we’re running into the ground freezing which impacts our ability to close our projects.”

The brief, called Late Utility Locates: Ontario Construction Industry’s Priority Solutions, states that governments recognize that delivering infrastructure projects is important to an economic recovery, but contractors are still facing long delays waiting for utilities to provide locates. For larger projects where there are up to 10 different companies responding to a request, some of the locates expire by the time all the locates are received.

Six-Point Plan:

  • The province restructure the board of directors of Ontario One Call so that half of the 12 members are non-utility representatives such as excavators, municipalities and the provincial government. Presently, nine of the board members represent utility members. Concerns have been expressed that directors representing utilities are unwilling to prosecute fellow utilities. As the Ontario One Call board is dominated by utility company representatives, there is no incentive for these companies to levy fines against themselves for not following the legislated timelines.
  • Stakeholders and Ontario One Call work together to maximize the sharing of locate responses among contractors and subcontractors working on the same construction site. Currently, multiple contractors bidding or working on a common construction project must each request their own locates.
  • All utilities, not just gas distributors, be encouraged to maximize the validity period of their locate tickets without impairing the health and safety of workers and the public. Longer locate ticket validity periods will reduce the number of locate requests and likely the number and/or severity of late locates.
  • Locate service providers be prequalified to locate all utilities in order to prevent companies from contracting their locates to a single company. The existing model creates artificial market scarcity by limiting a particular utility locate to a single company over a wide geographic area.
  • One Call and utilities be required to differentiate between single-address and multi-address locates. By modifying the reporting and record-keeping process, One Call could more easily identify problem areas related to the late delivery of locates and focus enforcement efforts.
  • Eliminate the need for further locates once a stationary vertical excavation has been dug below the depth of the lowest buried utility. This will lessen the burden on locate services and free up additional system capacity.

Manahan said he wants to see the board of directors of Ontario One Call restructured as soon as possible.

“Start out by restructuring One Call’s board of directors,” said Manahan. “The majority represents utilities like gas and cable companies so there is no built-in incentive for them to enforce penalties on themselves for not meeting the five-day period. That’s a problem. Our suggestion is for 50 per cent of the board to be comprised of non-utility representatives.”

McManus said he and the OSWCA members understand how important the locates are from a health and safety perspective, but would still like to see the wait times decreased and become faster and more predictable.

An example of the infrastructure system beneath roads. Photo: OSWCA

“From a health and safety perspective, we dig in the middle of the road and there’s all kinds of buried infrastructure there—gas lines, water, sewer, fibre optic cables, phone lines—we need to know where we’re digging before you take an excavator with a heavy shovel on the front and start digging into the road. You need to know where the lines are to protect ourselves and the precious infrastructure underneath,” he said. “If you dig without those locates and you don’t know where that infrastructure is buried you can strike a line. There’s been incidents before where people have been injured from striking lines.

“It’s absolutely imperative to have these markings on the ground so we know what is underneath our digging area,” McManus.

McManus said faster and more predictable locates would help a lot.

“The predictability of all this is probably the most important. If we could count on locates happening when they’re designed to, it would at least give us an idea of how to plan and workaround projects. I hope the government is beginning to grasp how important the impact of the slow downs and delays are, especially since they are investing in the infrastructure.”

 

 

 

 

 

 

 


Print this page

Advertisement

Stories continue below