B.C. building bridges to battle highway washouts due to floods

B.C. Ministry of Transportation and Infrastructure
June 06, 2018
By B.C. Ministry of Transportation and Infrastructure
B.C. building bridges to battle highway washouts due to floods
Photo: B.C. Ministry of Transportation and Infrastructure
June 6, 2018 - Work has started at five locations west of Chetwynd, B.C. to build robust, modern bridges that will allow people to travel safely and efficiently along Highway 97, especially in the event of heavy rain and flooding.

The ministry is investing $26.8 million on this flood mitigation strategy for the area. These projects are in addition to recovery work that has been ongoing since June 2016, when severe flooding caused extensive damage throughout the Peace District.

“The 2016 floods caused a lot of hardship for people in the Peace District, and we want to make sure our infrastructure can withstand future flooding events,” said Claire Trevena, Minister of Transportation and Infrastructure. “These are significant infrastructure projects which will boost safety and reliability for people travelling on Highway 97, particularly during heavy rain.”

Existing culverts at the five locations below are being replaced with modern two-lane bridges capable of withstanding a 200-year flood level. New highway approaches are being constructed on both sides of each bridge, and works will be done to stabilize the creek banks.

Bowlder Creek
Location: Highway 97, approximately 23 kilometres west of Chetwynd
Contractor: Formula Contractors Ltd. from Prince George
Total project cost: $7.1 million

Commotion Creek
Location: Highway 97, approximately 20 kilometres west of Chetwynd
Contractor: Cewe Infrastructure Ltd. from North Vancouver
Total project cost: $7.3 million

Stone Creek
Location: Highway 97, approximately 16 kilometres southwest of Chetwynd
Contractor: Surespan Construction Ltd. from North Vancouver
Total project cost: $4.6 million

Tippy Corner Creek
Location: Highway 97, approximately 45 kilometres west of Chetwynd
Contractor: Surespan Construction Ltd. from North Vancouver
Total project cost: $3.8 million

Willow Flats
Location: Highway 97, approximately 42 kilometres southwest of Chetwynd
Contractor: Surespan Construction Ltd. from North Vancouver
Total project cost: $4 million

Construction on these five projects has started, and is expected to be substantially complete by fall 2018.




Add comment


Security code
Refresh

Subscription Centre

 
New Subscription
 
Already a Subscriber
 
Customer Service
 
View Digital Magazine Renew

Most Popular

Latest Events

BCRB Fall Conference
September 16-18, 2018
CTAA Annual Convention
November 11-14, 2018
SHCA Annual Fall Convention
November 15-16, 2018

We are using cookies to give you the best experience on our website. By continuing to use the site, you agree to the use of cookies. To find out more, read our Privacy Policy.