| MAGAZINE | ||||
|---|---|---|---|---|
|
| MARKETPLACE | |||
|---|---|---|---|
|
|
|
| COMMUNITY | |||
|---|---|---|---|
|
| RESOURCES | |||||
|---|---|---|---|---|---|
|
|
|
![]() |
B.C. Roadbuilder tackles construction challenges A successful highway project through spectacular scenery has had its share of challenges |
| Written by Andy Bateman | |
For travellers on Highway 97, British Columbia’s north south arterial route, the Okanagan corridor between Kelowna and Penticton has often been one of the highway’s most memorable stretches, in terms of spectacular scenery as well as frustrating traffic congestion on winding two lane sections.
For the roadbuilder on a major highway upgrade project there, the expected challenges of construction through this rugged terrain were accompanied by unexpected natural events including a potential rock slip and wildlife rescue.
Material extraction and haulage has been a major component of the job, with some 1,100,000 m3 of rock removal and 1,200,000 m3 of dirt removal. Both materials have been used for embankment fill, while excess rock has been stockpiled and crushed on site for roadbase and asphalt aggregates. At the design stage, it was recognized that the new road alignment would require road closures and several focus groups were held by the province’s Ministry of Transportation to reduce construction impacts on the travelling public. Dimond notes that over fifty stakeholders were consulted and this input, supported by traffic data confirmed that night closure windows would be the best solution wherever possible. Traffic data indicated that 14,000 vehicles travelled this section of Highway 97 during daylight hours in the peak season compared to an hourly average of only 50 vehicles at night. Another important consideration at the design stage was the project’s extensive drilling and blasting requirements. It was decided early on that night blasting was impractical for safety reasons, so a number of mitigation measure were put in place to minimise traffic delays resulting from blasting during the daylight hours. As Dimond points out, the process of blasting on a roadbuilding project is significantly more involved than quarry blasting where public access is restricted, uniform rock faces are often already developed and shot rock is often left in place for some time. Contrast that to highway blasting, where the process requires closure of the blast zone to the public before the blast and the immediate removal of shot rock after the blast before the highway can be reopened. In terms of the blasting process itself, Dimond estimates that about 700,000 kg of explosives have been used on the project in total. Here again, advance work was done at the design stage, with a pre-blasting analysis performed to consider the effects of blasting on the local population. The resulting blasting procedures were site specific, with a project staff member present at locations that might have been vulnerable during a blast. Blast patterns varied according to local rock conditions, although a common blast pattern consisted of 16 to 50 holes, each 100mm in diameter in a 3m by 3m pattern. The backline was drilled at 0.75m spacing with 75mm holes with buffer holes at 2m spacing. To complete this work, subcontractor Paramount Drilling and Blasting utilised two Sandvik Tamrock Ranger 700 drill rigs, one Ranger 800, one 1500 Ranger, a tank drill, and an excavator drill. A typical blast yielded between 3,000m3 and 10,000 m3 of rock Holes were charged with a cast booster or emulsion (1.5x8”) primer and 25 to 50 kg of ANFO (Ammonium nitrate – fuel oil) blasting agent, with non-electrical initiation through shock-tube assembly with 25 millisecond delays between holes and 500 ms down the hole detonation. Of all the blasting work completed on this project, probably the best known was the remedial work following the discovery of a huge section of unstable rock in October 2008. (See sidebar: Unstable rock discovery and treatment). Material excavation and haulage on this project was completed by an extensive mobile equipment fleet that included Caterpillar D10 and D8 dozers, Komatsu PC 1250 LC excavator, and four Caterpillar 775F haul trucks. Additional equipment included a John Deere 450CLC, Komatsu PC400LC-8 and Volvo 210B excavators, four Caterpillar 740 Articulated Dump Trucks, six Terex TA40 articulated rock trucks, six Kenworth Heavy Duty highway trucks with side dump and end dump trailers, two Caterpillar graders (14G + new model rental) and several Bomag BW213DH pad foot compactors equipped with Bomag’s Variocontrol Intelligent Compaction system as well as a fleet of mechanics service trucks, water trucks, fuelling trucks and pickup trucks. Several other hired excavators were used on an as needed basis. Arthon also completed all gravel production with an Elrus spread comprised of a 2442 primary jaw crusher, Sandvik H3000 and H4000 cone crushers, a 6x20 inclined screen deck, Elrus conveyors and surge bins, powered by a 400kW power plant. Two Volvo L330 wheel loaders were on raw material supply and product handling duty in support. The paving of the 7km four lane project includes 36,000 tonnes of Superpave mix and some 3,000 tonnes of Class 1 medium mix for side roads and off-highway intersections. Peter’s Bros. Construction Ltd. from Penticton are providing the paving using a Roadtec RP195 Paver, a Roadtec RX60C Milling Machine, Caterpillar 634C, Ingersoll Rand PT 240, and Dynapac CC424 compactors, with the paving train supplied by a 300 tonne per hour Aesco – Matsen asphalt plant set up in the material stockpile area, high above the highway. Environmental protection measures are now an integral part of virtually all major roadbuilding projects and this job was no exception. Measures included the use of two dedicated water trucks to minimise fugitive dust generation on adjacent dirt side roads as well as portions of the highway itself. On this project, the Ministry of Transportation also engaged a team of Qualified Environmental Professionals (QEPs) and goat specialists to monitor the activity of the region’s mountain goats and ensure their protection from construction activity. Prior to excavating operations, for instance, the QEP’s performed a sweep of the area to identify and develop mitigation measures to protect the goat population and other wildlife. On that note, Arthon Contractors made the news again with the rescue of the mountain goat “Houdini” from the same rock crevice that triggered the rock slip prevention program in October 2008. Arthon’s key individuals who have run and completed this project include project manager Graham Bennison, chief superintendent and partner Guy Ferrari, Superintendent Jim Masson, with Dimond, a Gold Seal Certified project manager, in charge of Quality Control, Traffic, Safety & Contract Administration.
|
||||||||||||||||||||||||||||
|
|
| Related Articles |
|---|
|
Surveying the landscape by James Careless | 08/06/2010 Recycle plant pays dividends for Lafarge by Andy Bateman | 08/06/2010 Moving mountains by Treena Hein | 08/06/2010 Pave the way to profits by Mike Devine | 08/06/2010 Bauma 2010 Preview by Aggregates & Roadbuilding | 02/25/2010 |





.jpg)
.jpg)
.jpg)
.jpg)
.jpg)
.jpg)